Completion of the Elevator Shaft
(July 13, 2018)

Continued Sheet Rocking of Walls and New Copper Pipes in the Boiler Room
(June 25, 2018)

Construction of the Elevator Shaft & Slab for Heating and A/C System
(Beginning June 12, 2018)

Sheet Rocking and Enclosing of Walls
(June 11, 2018)

Sheet Rocking of Rooms and Ceilings
(June 4, 2018)

Framing of Rooms and Installation of Heating & AC Ducts
(April 30, 2018)

Newly Installed Windows & Excavation of the Elevator Pit
(March 22, 2018)

Outer/Inner Framing & Installation of New Windows
(March 19, 2018)

Ready to start construction this week!
(February 26, 2018)

More Demolition
(February 19, 2018)

New Roof and Demolition of the Basement Level
(February 2, 2018)

 

Demolition of the Roof
(January 29, 2018)

 

Demolition & Asbestos Removal
(July 2017)